Anson Solar Center, Phase II
200.9 MW generation in Jones, TX · In queue since June 2017 · Proposed COD March 2026
200.9 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
7y 2m
IA → COD
1y 7m
Total Duration
7y 2m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-31
The Anson Solar Center, Phase II project is a proposed 200.9 MW solar generation project located in Jones County, Texas. The developer is Anson Solar Center 2, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-20INR0242, with an interconnection queue entry date of June 23, 2017. The proposed commercial operation date is March 31, 2026.
The project's interconnection agreement (IA) has been executed as of August 15, 2024. The point of interconnection is an existing tap to the 345 kV 68004 Phantom Hill station. This development is linked to the existing operating plant ANSON Solar Center, LLC (EIA plant ID 64026).
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anson Solar Center 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
existing tap 345 kV 68004 Phantom Hill station
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ANSON1_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Anson Solar Center, Phase II