Water Valley Wind Energy
180 MW generation in Tom Green, TX · In queue since January 2019 · Proposed COD December 2027
180 MW
Capacity
1
Components
Wind
7y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
Water Valley Wind Energy is a proposed wind generation project located in Tom Green County, Texas, with a total capacity of 180 MW. The developer is Water Valley Wind Energy, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0247, with a queue entry date of January 15, 2019, and a proposed commercial operation date of December 15, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Water Valley Wind Energy operating plant (EIA ID 62846). Recent news coverage of the project includes 27 articles related to industry, regulatory, and grid topics.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Water Valley Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV 76009 Twin Buttes to 76090 Divide Double Circuit
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Colorado River Municipal Water District #4 Substation