DAMAZO (Second Division) SOLAR
100.2 MW generation in Brazoria, TX · In queue since March 2019 · Proposed COD December 2025
100.2 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
Signed Oct 2020
Queue → IA
1y 7m
IA → COD
5y 2m
Total Duration
1y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-31
The DAMAZO (Second Division) SOLAR project is a proposed 100.2 MW solar generation project located in Brazoria County, Texas. The developer is TX Gulf Solar 1 LLC. This project is in the ERCOT interconnection queue as entry ERCOT-20INR0248, with a queue entry date of March 28, 2019, and a proposed commercial operation date of December 31, 2025.
The project's Interconnection Agreement (IA) was executed on October 14, 2020. The project is linked to the existing Second Division Solar operating plant (EIA ID 65981). The point of interconnection is Tap 138 kV SANBER_POI_8 (Bus# 43110) to WEST COLUMBIA (Bus# 43380) Ckt 60 Line.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TX Gulf Solar 1 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV SANBER_POI_8 (Bus# 43110) to WEST COLUMBIA (Bus# 43380) Ckt 60 Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DAG_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about DAMAZO (Second Division) SOLAR