San Bernard Solar II
102 MW generation in Wharton, TX · In queue since March 2019
102 MW
Capacity
1
Components
Solar
7y 2m
In Queue
Facility Study
IA Status
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The San Bernard Solar II project is a proposed 102 MW solar generation facility in Wharton County, Texas. Developed by San Bernard Solar II, LLC, the project entered the ERCOT interconnection queue as entry 20INR0259 on March 25, 2019. Its interconnection status is currently in the Facility Study phase. The project has appeared in recent news coverage.
The proposed project consists of 102 MW of solar photovoltaic generation capacity. The project's status is currently listed as suspended within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
San Bernard Solar II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26