Texas Solar Nova 2
201.14 MW generation in Kent, TX · In queue since June 2019 · Proposed COD December 2024
201.14 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Jul 2021
Queue → IA
2y 1m
IA → COD
3y 5m
Total Duration
2y 1m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-12-31
Texas Solar Nova 2 is a proposed 201.14 MW solar generation project located in Kent County, Texas. The developer is TEXAS SOLAR NOVA 2, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-20INR0269, with a queue entry date of June 24, 2019, and a proposed commercial operation date of December 31, 2024. The Interconnection Agreement (IA) was executed on July 16, 2021.
The proposed project is linked to the existing Texas Solar Nova 2 operating plant (EIA ID 65660). It has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kent
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TEXAS SOLAR NOVA 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV 59909 WETT Nova Prime
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NOVA1SLR_ALL