Air Products GCA
14 MW generation in Galveston, TX · In queue since June 2018 · Proposed COD December 2025
14 MW
Capacity
1
Components
Gas
7y 11m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
2y 2m
IA → COD
5y 4m
Total Duration
2y 2m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-12-31
The Air Products GCA is a proposed 14 MW gas-fired generation project located in Galveston County, Texas. Developed by Air Products, the project is interconnected within the ERCOT region under queue ID ERCOT-21INR0012. The project entered the interconnection queue on June 7, 2018, with a proposed commercial operation date of December 31, 2025. An Interconnection Agreement (IA) was executed on August 7, 2020.
The point of interconnection is the 39140 TNTxCityMain 69kV substation, which will be upgraded to 138kV. The Air Products GCA project has been the subject of recent news coverage, with five articles related to industry trends and deals.
Generated from interconnection queue and public data sources
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Air Products
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
39140 TNTxCityMain 69kV (Will be upgraded to 138kV)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26