Red Holly Solar
260 MW generation in Dawson, TX · In queue since July 2018 · Proposed COD June 2027
260 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Status
Signed Oct 2020
Queue → IA
2y 3m
IA → COD
6y 8m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-01
Red Holly Solar is a proposed 260 MW solar generation project located in Dawson County, Texas. The developer is GreenGo Energy. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0022, with a queue entry date of July 11, 2018. The proposed commercial operation date is June 1, 2027.
The project's interconnection agreement (IA) was executed on October 19, 2020. The point of interconnection (POI) is at the tap 345kV 59900 Longdraw - 79641 Farmland.
Generated from interconnection queue and public data sources
State
TX
County
Dawson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GreenGo Energy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 59900 Longdraw - 79641 Farmland
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.