Red Holly Storage 1 (ERCOT-21INR0029) — Project Summary

Queue ID
ERCOT-21INR0029
Capacity
50 MW
Technology
Battery
Status
active
Location
Dawson, TX
Region
ERCOT
Developer
GreenGo Energy
IA Status
IA Executed

Red Holly Storage 1

ERCOT-21INR0029BetaActiveBatteryERCOTLBNL + Live

50 MW storage in Dawson, TX · In queue since July 2018 · Proposed COD May 2028

50 MW

Capacity

1

Components

Battery

7y 10m

In Queue

IA Executed

IA Status

Signed Oct 2020

Interconnection

Queue → IA

2y 3m

IA → COD

7y 7m

Total Duration

2y 3m

Construction75%
Queue EntryJul 11, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 19, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-05-30

About

Red Holly Storage 1 is a proposed 50 MW battery storage project located in Dawson County, Texas. The developer is GreenGo Energy. The project is interconnected within the ERCOT region and entered the ERCOT queue as ERCOT-21INR0029 on July 11, 2018. The proposed commercial operation date is May 30, 2028.

The project's Interconnection Agreement (IA) was executed on October 19, 2020. The point of interconnection is tap 345kV 59900 Longdraw - 79641 Farmland. The Red Holly Storage 1 project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Dawson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

GreenGo Energy

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 59900 Longdraw - 79641 Farmland

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Red Holly Storage 1