Eastbell Milam Solar
244.86 MW generation in Milam, TX · In queue since October 2018 · Proposed COD October 2025
244.86 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Executed
IA Status
Signed Sep 2022
Queue → IA
3y 11m
IA → COD
3y 1m
Total Duration
3y 11m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
The Eastbell Milam Solar project is a proposed 244.86 MW solar generation project located in Milam County, Texas. The developer is EDP Renewables North America LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0203, with a queue entry date of October 10, 2018, and a proposed commercial operation date of October 31, 2025.
The project's Interconnection Agreement (IA) has been executed as of September 2, 2022. The point of interconnection (POI) is the 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EDP RENEWABLES NORTH AMERICA LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Eastbell Milam Solar