251.28 MW generation in Wichita, TX · In queue since November 2018 · Proposed COD August 2027
251.28 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Aug 2022
Queue → IA
3y 9m
IA → COD
5 years
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-31
Adamstown Solar is a proposed 251.28 MW solar generation project located in Wichita County, Texas. The project, developed by Adams Creek Solar Project, LLC, is interconnected within the ERCOT region under queue ID ERCOT-21INR0210. It entered the interconnection queue on November 20, 2018, and has a proposed commercial operation date of August 31, 2027.
The project's Interconnection Agreement (IA) was executed on August 8, 2022, and its Point of Interconnection (POI) is at tap 345kV 1730 West Krum - 6111 Riley Ckt 2. The project is currently listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Adams Creek Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1730 West Krum - 6111 Riley Ckt 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HMNG_ESS_RN
- POI Substation
- West Krum Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.