Adamstown Solar (ERCOT-21INR0210) — Project Summary

Queue ID
ERCOT-21INR0210
Capacity
251.28 MW
Technology
Solar
Status
active
Location
Wichita, TX
Region
ERCOT
Developer
Adams Creek Solar Project, LLC
IA Status
IA Executed

Adamstown Solar

ERCOT-21INR0210BetaActiveSolarERCOTLBNL + Live

251.28 MW generation in Wichita, TX · In queue since November 2018 · Proposed COD August 2027

251.28 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Status

Signed Aug 2022

Interconnection

Queue → IA

3y 9m

IA → COD

5 years

Total Duration

3y 9m

Construction75%
Queue EntryNov 20, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 8, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-08-31

About

Adamstown Solar is a proposed 251.28 MW solar generation project located in Wichita County, Texas. The project, developed by Adams Creek Solar Project, LLC, is interconnected within the ERCOT region under queue ID ERCOT-21INR0210. It entered the interconnection queue on November 20, 2018, and has a proposed commercial operation date of August 31, 2027.

The project's Interconnection Agreement (IA) was executed on August 8, 2022, and its Point of Interconnection (POI) is at tap 345kV 1730 West Krum - 6111 Riley Ckt 2. The project is currently listed as active in the ERCOT interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wichita

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Adams Creek Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1730 West Krum - 6111 Riley Ckt 2

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
HMNG_ESS_RN
POI Substation
West Krum Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.