Maleza Solar (ERCOT-21INR0220) — Project Summary

Queue ID
ERCOT-21INR0220
Capacity
254.94 MW
Technology
Solar
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Brush Solar LLC
IA Status
IA Executed

Maleza Solar

ERCOT-21INR0220BetaActiveSolarERCOTLBNL + Live

254.94 MW generation in Wharton, TX · In queue since December 2018 · Proposed COD December 2028

254.94 MW

Capacity

1

Components

Solar

7y 5m

In Queue

IA Executed

IA Status

Signed Jan 2021

Interconnection

Queue → IA

2y 1m

IA → COD

7y 11m

Total Duration

2y 1m

Construction75%
Queue EntryDec 6, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 27, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-31

About

The Maleza Solar project is a proposed solar generation facility with a total capacity of 254.94 MW. It is located in Wharton County, Texas, and is being developed by Brush Solar LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-21INR0220, with a queue entry date of December 6, 2018, and a proposed commercial operation date of December 31, 2028.

The project has an executed Interconnection Agreement (IA), which was finalized on January 27, 2021. The point of interconnection (POI) is the tap Blue Hillje 345 kV Ckt.#27. The Maleza Solar project has appeared in recent news coverage regarding energy development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Brush Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap Blue _x0013_ Hillje 345 kv Ckt.#27

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Maleza Solar