La Casa Wind
148.4 MW generation in Stephens, TX · In queue since December 2018 · Proposed COD March 2026
148.4 MW
Capacity
1
Components
Wind
7y 5m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
4y 9m
IA → COD
2y 6m
Total Duration
4y 9m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-03-16
The La Casa Wind project is a proposed 148.4 MW wind generation facility in Stephens County, Texas. Developed by LA CASA WIND, LLC, the project entered the ERCOT interconnection queue as ERCOT-21INR0240 on December 28, 2018, and has a proposed commercial operation date of March 16, 2026. The project's Interconnection Agreement (IA) was executed on September 7, 2023.
The proposed project is linked to the existing La Casa Wind operating plant (EIA ID 66919). The point of interconnection is a new switching station: 138kV Graham Plant Switch - Breckenridge - Leon Switch. The La Casa Wind project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Stephens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LA CASA WIND, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
New switching station: 138kV Graham Plant Switch - Breckenridge - Leon Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LACASAWD_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26