Anson Solar Center, Phase III
200 MW generation in Jones, TX · In queue since June 2017 · Proposed COD June 2028
200 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
11 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The Anson Solar Center, Phase III is a proposed 200 MW solar generation project located in Jones County, Texas. The developer is Anson Solar Center 3, LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-21INR0247, with a queue entry date of June 23, 2017, and a proposed commercial operation date of June 1, 2028. Its interconnection status is currently in the Facility Study phase.
The Anson Solar Center, Phase III project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anson Solar Center 3, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 68000 WShack - 68001 Clayton
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.