Ulysses Solar
150 MW generation in Coke, TX · In queue since January 2019 · Proposed COD March 2027
150 MW
Capacity
1
Components
Solar
7y 4m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
3y 9m
IA → COD
4y 5m
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-02
The Ulysses Solar project is a proposed 150 MW solar generation facility in Coke County, Texas. Developed by BNB Tennyson Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-21INR0253, with a queue entry date of January 25, 2019. The proposed commercial operation date is March 2, 2027.
The project has an executed Interconnection Agreement (IA), dated October 3, 2022. The point of interconnection (POI) is at the tap 345kV 6444 Red Creek - 60040 Bluff Creek. The Ulysses Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Coke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BNB Tennyson Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 6444 Red Creek - 60040 Bluff Creek
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- San Angelo Red Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Ulysses Solar