Chariot Storage
50 MW storage in Limestone, TX · In queue since March 2019 · Proposed COD February 2028
50 MW
Capacity
1
Components
Battery
7y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-29
The Chariot Storage project is a proposed 50 MW battery storage development in Limestone County, Texas. The project, being developed by Chariot Storage LLC, is interconnected within the ERCOT region under queue ID ERCOT-21INR0260. It entered the queue on March 6, 2019, and has a proposed commercial operation date of February 29, 2028. Its interconnection status is currently in the Facility Study phase.
The project consists of 50 MW of battery storage capacity. The Chariot Storage project has been the subject of recent news coverage related to deals.
Generated from interconnection queue and public data sources
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Chariot Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 69kV 99 Ben Hur - 107 Prairie Hill
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Ben Hur Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Chariot Storage