Monarch Creek Wind
279 MW generation in Throckmorton, TX · In queue since April 2019 · Proposed COD September 2027
279 MW
Capacity
1
Components
Wind
7y 1m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
1y 4m
IA → COD
7y 1m
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-09-17
Monarch Creek Wind is a proposed wind generation project located in Throckmorton County, Texas. The project, being developed by Monarch Creek Wind Holdings, LLC, has a total capacity of 279 MW. It is interconnected within the ERCOT queue as entry ERCOT-21INR0263, with a queue entry date of April 25, 2019. The project's proposed commercial operation date is September 17, 2027, and its Interconnection Agreement (IA) was executed on August 24, 2020.
The proposed project's point of interconnection (POI) is the tap 345kV 11418 Tecumseh Creek Switch to 60515 Clear Crossing Switch. Monarch Creek Wind has been the subject of recent news coverage, with nine articles related to the grid and industry.
Generated from interconnection queue and public data sources
State
TX
County
Throckmorton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Monarch Creek Wind Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 11418 Tecumseh Creek Switch to 60515 Clear Crossing Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.