Fighting Jays Solar
351.29 MW generation in Fort Bend, TX · In queue since March 2019 · Proposed COD March 2025
351.29 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
Signed Jun 2020
Queue → IA
1y 3m
IA → COD
4y 9m
Total Duration
1y 3m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-29
The Fighting Jays Solar project is a proposed 351.29 MW solar generation facility in Fort Bend County, Texas. Developed by AP Solar Holdings, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-21INR0278. The project entered the interconnection queue on March 26, 2019, and has a proposed commercial operation date of March 29, 2025.
The project's Interconnection Agreement (IA) was executed on June 22, 2020. The point of interconnection is at tap 345kV 44000 WA Parish - 44200 Hillje c64. The Fighting Jays Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Fort Bend
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
AP Solar Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 44000 WA Parish - 44200 Hillje c64
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WAP_WAP_G7
- POI Substation
- W. A. Parish Station (345 kV)
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26