Halo Solar
254 MW generation in Bell, TX · In queue since January 2020
254 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Aug 2022
Queue → IA
2y 7m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Commercial operation date not yet determined
Halo Solar is a proposed solar generation project with a total capacity of 254 MW, located in Bell County, Texas. The project is being developed by Ben Milam Solar 3. It is listed in the ERCOT interconnection queue as entry ERCOT-21INR0304, with a queue entry date of January 22, 2020. The project's interconnection agreement was executed on August 18, 2022, and its current status is suspended.
The point of interconnection is at the tap 345kV 3687 Bell E - 39950 TNTNP One, one-fourth from Bell.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ben Milam Solar 3
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3687 Bell E - 39950 TNTNP One, one-fourth from Bell
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bell County Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Halo Solar