Board Creek Wind
299.2 MW generation in Navarro, TX · In queue since April 2019 · Proposed COD April 2026
299.2 MW
Capacity
1
Components
Wind
7y 1m
In Queue
IA Executed
IA Status
Signed Aug 2021
Queue → IA
2y 4m
IA → COD
4y 8m
Total Duration
2y 4m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-04-30
The Board Creek Wind project is a proposed wind generation facility with a total capacity of 299.2 MW. Located in Navarro County, Texas, the project is being developed by Limestone Wind Project, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-21INR0324, with a queue entry date of April 24, 2019, and a proposed commercial operation date of April 30, 2026. The project's Interconnection Agreement (IA) was executed on August 19, 2021.
The point of interconnection (POI) is the 345kV 3386 Outlaw Switch. The Board Creek Wind project has been the subject of recent news coverage, with 72 articles related to its development, regulatory status, and industry impact.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Limestone Wind Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV 3386 Outlaw Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26