Dove Run Solar (ERCOT-21INR0326) — Project Summary

Queue ID
ERCOT-21INR0326
Capacity
120.86 MW
Technology
Solar
Status
active
Location
Duval, TX
Region
ERCOT
Developer
Dove Run Solar Project, LLC
IA Status
IA Executed

Dove Run Solar

ERCOT-21INR0326BetaActiveSolarERCOTLBNL + Live

120.86 MW generation in Duval, TX · In queue since May 2019 · Proposed COD October 2027

120.86 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection

Queue → IA

4y 5m

IA → COD

4 years

Total Duration

4y 5m

Construction75%
Queue EntryMay 7, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 31, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-15

About

Dove Run Solar is a proposed 120.86 MW solar generation project located in Duval County, Texas. The developer is Dove Run Solar Project, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0326, with a queue entry date of May 7, 2019. The proposed commercial operation date is October 15, 2027.

The project's Interconnection Agreement (IA) has been executed as of October 31, 2023. The point of interconnection (POI) is at tap 138kV 8510 Falfurrias - 8695 Crestonio. The Dove Run Solar project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Duval

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Dove Run Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138kV 8510 Falfurrias - 8695 Crestonio

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
FALFUR_RN
POI Substation
Falfurrias Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Dove Run Solar