Cuhullin Wind
310.2 MW generation in Bee, TX
310.2 MW
Capacity
1
Components
Wind
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Cuhullin Wind project is a 310.2 MW wind generation facility located in Bee County, Texas. The project is listed in the ERCOT interconnection queue as entry 21INR0348.
The project's status is currently listed as suspended within the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Bee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.