Eliza Solar
151.7 MW generation in Kaufman, TX · In queue since June 2019 · Proposed COD December 2025
151.7 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Aug 2022
Queue → IA
3y 2m
IA → COD
3y 4m
Total Duration
3y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-18
The Eliza Solar project is a proposed 151.7 MW solar generation project located in Kaufman County, Texas. The developer is Ables Springs Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0368, with a queue entry date of June 21, 2019. The proposed commercial operation date is December 18, 2025.
The project's Interconnection Agreement (IA) was executed on August 4, 2022. The point of interconnection is the tap 345kV 2478 Royse - 3103 Shamburger. The Eliza Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ables Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 2478 Royse - 3103 Shamburger
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- V2_DGR1_RN
- POI Substation
- Royse Substation