HIP Solar Project
137.6 MW generation in Leon, TX · In queue since August 2019 · Proposed COD May 2027
137.6 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
The HIP Solar Project is a proposed 137.6 MW solar generation project located in Leon County, Texas. The project, developed by ConnectGen Operating LLC, is in the ERCOT interconnection queue as entry ERCOT-21INR0371, with a queue entry date of August 16, 2019. The proposed commercial operation date is May 1, 2027, and the project's interconnection status is currently in the Facility Study phase.
The HIP Solar Project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ConnectGen Operating LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 967 Gibbons Creek - 46020 Limestone ckt 50
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Gibbons Creek Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26