HIP ESS Project
60 MW generation in Leon, TX
60 MW
Capacity
1
Components
Other
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The HIP ESS Project is a proposed 60 MW energy storage project in Leon County, Texas. The project, listed in the ERCOT interconnection queue as ERCOT-21INR0390, consists of 60 MW of unspecified "Other" technology.
The project's interconnection request was submitted to ERCOT, but its current status is listed as "suspended". No proposed commercial operation date or interconnection agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about HIP ESS Project