Young Wind
499.14 MW generation in Young, TX · In queue since July 2019 · Proposed COD March 2025
499.14 MW
Capacity
1
Components
Wind
6y 10m
In Queue
IA Executed
IA Status
Signed Feb 2022
Queue → IA
2y 7m
IA → COD
3y 1m
Total Duration
2y 7m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-03-14
The Young Wind project is a proposed wind generation facility with a total capacity of 499.14 MW. Located in Young County, Texas, the project is being developed by Young Wind, LLC. It is listed in the ERCOT interconnection queue as ERCOT-21INR0401, with an original queue entry date of July 29, 2019, and a proposed commercial operation date of March 14, 2025. The project's interconnection agreement was executed on February 18, 2022.
The proposed project is linked to the existing Young Wind operating plant (EIA ID 65763). Recent news coverage indicates activity related to the project, with nine articles appearing in the news, covering topics such as deals, industry trends, and regulatory matters.
Generated from interconnection queue and public data sources
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Young Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60515 Clear Crossing - 1421 Willow Creek
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- YNG_WND_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26