Jayhawk Solar (ERCOT-21INR0414) — Project Summary

Queue ID
ERCOT-21INR0414
Capacity
101.5 MW
Technology
Solar
Status
active
Location
Mitchell, TX
Region
ERCOT
Developer
Renewable Energy Ventures, LLC
IA Status
Facility Study

Jayhawk Solar

ERCOT-21INR0414BetaActiveSolarERCOTLBNL + Live

101.5 MW generation in Mitchell, TX · In queue since August 2019 · Proposed COD October 2025

101.5 MW

Capacity

1

Components

Solar

6y 9m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

6y 2m

Schedule

6 months past proposed COD

Facilities Study50%
Queue EntryAug 5, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-30

About

The Jayhawk Solar project is a proposed 101.5 MW solar generation facility in Mitchell County, Texas. The project, developed by Renewable Energy Ventures, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-21INR0414, with a queue entry date of August 5, 2019. The proposed commercial operation date is October 30, 2025. The project's interconnection status is currently in the Facility Study phase, and it is slated to connect to the tap 345kV 1030 Morgan - 76030 Gasconades point of interconnection.

The Jayhawk Solar project has been the subject of recent news coverage, with three articles categorized as industry news and deals.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Mitchell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Renewable Energy Ventures, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1030 Morgan - 76030 Gasconades

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MGSES_CT123
POI Substation
Morgan Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Jayhawk Solar