Armadillo Solar
200.09 MW generation in Navarro, TX · In queue since August 2019 · Proposed COD December 2026
200.09 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
Signed Feb 2021
Queue → IA
1y 6m
IA → COD
5y 10m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Armadillo Solar is a proposed solar generation project located in Navarro County, Texas, with a total capacity of 200.09 MW. The developer is Armadillo Solar Center, LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-21INR0421, with a queue entry date of August 28, 2019, and a proposed commercial operation date of December 31, 2026. The interconnection agreement (IA) has been executed as of February 2, 2021.
The proposed project is linked to the existing Armadillo Solar Center operating plant (EIA plant ID 64349). Recent news coverage of the project includes reports on industry developments and deals.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Armadillo Solar Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3387 Revolution 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Armadillo Solar