San Bernard Storage
100.62 MW generation in Wharton, TX · In queue since November 2019
100.62 MW
Capacity
1
Components
Other
6y 6m
In Queue
Facility Study
IA Status
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The San Bernard Storage project is a proposed 100.62 MW energy storage development in Wharton County, Texas. The project, developed by San Bernard Storage, LLC, is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-21INR0465 on November 27, 2019. Its interconnection status is currently in the Facility Study phase.
The project consists of 100.62 MW of "Other" energy storage technology. The proposed commercial operation date is not available, and the project's status is currently listed as suspended. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
San Bernard Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.