Pandora Solar
252 MW generation in Wilson, TX
252 MW
Capacity
1
Components
Solar
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Pandora Solar project is a proposed 252 MW solar generation facility in Wilson County, Texas. The project is located within the Electric Reliability Council of Texas (ERCOT) region and is listed in the ERCOT interconnection queue as entry 21INR0486.
The project's current status in the interconnection queue is suspended.
Generated from interconnection queue and public data sources
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pandora Solar