Samson Solar 2
203 MW generation in Lamar, TX · In queue since January 2020 · Proposed COD May 2026
203 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
7 months
IA → COD
5y 9m
Total Duration
7 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-30
The proposed Samson Solar 2 project is a 203 MW solar generation facility in Lamar County, Texas. Developed by Samson Solar Energy II LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-21INR0490. The project entered the queue on January 13, 2020, and has a proposed commercial operation date of May 30, 2026.
The project's Interconnection Agreement (IA) was executed on August 27, 2020. Samson Solar 2 is linked to the existing Samson Solar Energy II LLC operating plant (EIA plant ID 63882). The point of interconnection is the 345 kV TTRSW 11688. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Samson Solar Energy II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV TTRSW 11688
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- IMP_RN1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Samson Solar 2