Samson Solar 3 (ERCOT-21INR0491) — Project Summary

Queue ID
ERCOT-21INR0491
Capacity
250 MW
Technology
Solar
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Samson Solar Energy III LLC
IA Status
IA Executed

Samson Solar 3

ERCOT-21INR0491BetaActiveSolarERCOTLBNL + Live

250 MW generation in Lamar, TX · In queue since January 2020 · Proposed COD June 2026

250 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Status

Signed Aug 2020

Interconnection

Queue → IA

7 months

IA → COD

5y 10m

Total Duration

7 months

Construction75%
Queue EntryJan 13, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 27, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-06-30

About

Samson Solar 3 is a proposed solar generation project with a total capacity of 250 MW, located in Lamar County, Texas. The developer is Samson Solar Energy III LLC. The project is actively listed in the ERCOT interconnection queue as entry ERCOT-21INR0491, with a queue entry date of January 13, 2020, and a proposed commercial operation date of June 30, 2026.

The project's interconnection agreement (IA) has been executed as of August 27, 2020. The point of interconnection (POI) is at the tap of both 345kV 1685 FarmersVl - 1695 Moses ckts. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Lamar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Samson Solar Energy III LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap both 345kV 1685 FarmersVl - 1695 Moses ckts

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Samson Solar 3