Stockyard Grid Batt
150.6 MW storage in Tarrant, TX · In queue since January 2020 · Proposed COD December 2026
150.6 MW
Capacity
1
Components
Battery
6y 4m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
2y 9m
IA → COD
4y 2m
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-12-31
The Stockyard Grid Batt project is a proposed 150.6 MW battery storage project located in Tarrant County, Texas. Developed by Stockyard Grid, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-21INR0492, with a queue entry date of January 13, 2020. The project's proposed commercial operation date is December 31, 2026, and its Interconnection Agreement (IA) was executed on October 26, 2022.
The proposed project's point of interconnection (POI) is at the 2082 Hicks 138kV location. The Stockyard Grid Batt project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Tarrant
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stockyard Grid, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2082 Hicks 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CHISMGRD_RN
- POI Substation
- Hicks Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.