Angels Creek
31.68 MW storage in Webb, TX · In queue since June 2020 · Proposed COD June 2026
31.68 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The Angels Creek project is a proposed 31.68 MW battery storage development in Webb County, Texas. The project, developed by Angels Creek LLC, is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-21INR0508 on June 3, 2020. The proposed commercial operation date is June 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists solely of battery storage, with a total capacity of 31.68 MW. The point of interconnection is the 5888 Bruni 69kV substation. The project is currently listed as active within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Angels Creek LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5888 Bruni 69kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bruni Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Angels Creek