Tidwell Prairie Storage 1
200.6 MW storage in Robertson, TX · In queue since July 2020 · Proposed COD June 2025
200.6 MW
Capacity
1
Components
Battery
5y 10m
In Queue
IA Executed
IA Status
Signed Nov 2022
Queue → IA
2y 4m
IA → COD
2y 7m
Total Duration
2y 4m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-01
Tidwell Prairie Storage 1 is a proposed 200.6 MW battery storage project located in Robertson County, Texas. The project is being developed by Tidwell Prairie LLC and is interconnected within the ERCOT region under queue ID ERCOT-21INR0517. The project entered the queue on July 24, 2020, and has a proposed commercial operation date of June 1, 2025. The Interconnection Agreement (IA) for the project was executed on November 3, 2022.
The proposed project is linked to the existing Tidwell Prairie II operating plant (EIA plant ID 68425). Recent news coverage indicates activity related to deals involving the project.
Generated from interconnection queue and public data sources
State
TX
County
Robertson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tidwell Prairie LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
39950 TNP ONE PLANT 345kV - 3400 TWIN OAK
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TDWLPR_1_RN
- POI Substation
- Phillips Coal Substation