Blue Jay Solar II
68.95 MW generation in Grimes, TX · In queue since April 2021 · Proposed COD October 2025
68.95 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
Signed Oct 2020
IA → COD
5 years
Total Duration
5y 1m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
Blue Jay Solar II is a proposed solar generation project located in Grimes County, Texas, with a total capacity of 68.95 MW. The project, developed by Blue Jay Solar I, LLC, consists of 68.95 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-21INR0538, with a queue entry date of April 13, 2021, and a proposed commercial operation date of October 31, 2025. The project's Interconnection Agreement (IA) has been executed as of October 26, 2020.
The proposed project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blue Jay Solar I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
4 Iola 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BLUEJAY_RN
- POI Substation
- Iola Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Blue Jay Solar II