Delilah Solar 1
300 MW generation in Lamar, TX · In queue since November 2018 · Proposed COD May 2026
300 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Dec 2020
Queue → IA
2y 1m
IA → COD
5y 5m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-30
Delilah Solar 1 is a proposed 300 MW solar generation project located in Lamar County, Texas. The developer is Delilah Solar Energy LLC. This project is in the ERCOT interconnection queue as entry ERCOT-22INR0202, with a queue entry date of November 20, 2018, and a proposed commercial operation date of May 30, 2026.
The project's interconnection agreement (IA) has been executed as of December 22, 2020. The point of interconnection (POI) is at the tap of both 345kV 1685 FarmersVl - 1695 Moses ckts. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Delilah Solar Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap both 345kV 1685 FarmersVl - 1695 Moses ckts
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.