Felix North Solar
100.54 MW generation in Wilbarger, TX · In queue since January 2019 · Proposed COD December 2028
100.54 MW
Capacity
1
Components
Solar
7y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
9y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The Felix North Solar project is a proposed 100.54 MW solar generation facility in Wilbarger County, Texas. Developed by Crescent Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0209, with a queue entry date of January 17, 2019. Its proposed commercial operation date is December 31, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 100.54 MW of solar photovoltaic generation. It is planned to connect to the grid at the 6101 Riley 345kV point of interconnection. The Felix North Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Crescent Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 Riley 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.