Greyhound Solar 2
500 MW generation in Ector, TX · In queue since May 2019 · Proposed COD November 2028
500 MW
Capacity
1
Components
Solar
7 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
9y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-17
Greyhound Solar 2 is a proposed 500 MW solar generation project located in Ector County, Texas. The developer is listed as Greyhound Solar 2. This project is in the ERCOT interconnection queue as entry ERCOT-22INR0218, with a queue entry date of May 14, 2019. The proposed commercial operation date is November 17, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The Greyhound Solar 2 project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greyhound Solar 2
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV dbl ckt 11010 Wolf - 1018 Moss and 11008 Wolf - 11028 Odessa
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTop solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.