Lamkin Solar
101.5 MW generation in Comanche, TX · In queue since June 2019 · Proposed COD August 2027
101.5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-08
The Lamkin Solar project is a proposed 101.5 MW solar generation facility in Comanche County, Texas. Developed by Commanche Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0220, with a queue entry date of June 24, 2019. The proposed commercial operation date is August 8, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 69kV 258 Hamilton - 273 Gustine. The Lamkin Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Commanche Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 69kV 258 Hamilton - 273 Gustine
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Hamilton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lamkin Solar