Bright Arrow Solar
305.07 MW generation in Hopkins, TX · In queue since February 2020 · Proposed COD March 2025
305.07 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Status
Signed Feb 2021
Queue → IA
1 year
IA → COD
4y 1m
Total Duration
1 year
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
Bright Arrow Solar is a proposed 305.07 MW solar generation project located in Hopkins County, Texas. Developed by RWE Solar Development, LLC, the project entered the ERCOT interconnection queue as ERCOT-22INR0242 on February 12, 2020, with a proposed commercial operation date of March 1, 2025. The project's Interconnection Agreement (IA) was executed on February 18, 2021. The point of interconnection is the 11689 CYCLONE 345 KV substation.
The proposed project is linked to the existing Bright Arrow Solar, LLC operating plant (EIA plant ID 66688). Bright Arrow Solar has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11689 CYCLONE 345 KV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BR_ARROW_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.