Painted Horse Solar
200.58 MW generation in Wilson, TX · In queue since February 2020 · Proposed COD December 2025
200.58 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
5y 10m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-15
The Painted Horse Solar project is a proposed 200.58 MW solar generation facility in Wilson County, Texas. Developed by RWE Solar Development, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0243, with a queue entry date of February 12, 2020. The proposed commercial operation date is December 15, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is tap 345kV 5915 STP - 5133 Elm Creek ckt 1. The Painted Horse Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5915 STP - 5133 Elm Creek ckt 1
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.