Razorbill Solar
240 MW generation in Matagorda, TX · In queue since January 2020 · Proposed COD December 2027
240 MW
Capacity
1
Components
Solar
6y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
Razorbill Solar is a proposed 240 MW solar generation project located in Matagorda County, Texas. The project, being developed by RWE Solar Development, LLC, is in the ERCOT interconnection queue as entry ERCOT-22INR0244, with a queue entry date of January 2, 2020. The proposed commercial operation date is December 15, 2027. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for Razorbill Solar is the tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.