Corazon Solar Phase II
203.9 MW generation in Webb, TX · In queue since December 2019 · Proposed COD June 2028
203.9 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
8 months
IA → COD
7y 10m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-01
The Corazon Solar Phase II project is a proposed 203.9 MW solar generation project located in Webb County, Texas. The project, developed by BAYWA R.E. SOLAR PROJECTS, is in the ERCOT interconnection queue as entry ERCOT-22INR0257, with a queue entry date of December 19, 2019. The project's proposed commercial operation date is June 1, 2028.
The project has an Interconnection Agreement (IA) executed on August 4, 2020. The Point of Interconnection (POI) is the 80219 Lobo 345kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BAYWA R.E. SOLAR PROJECTS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80219 Lobo 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WFTANK_ESS1
- POI Substation
- Lobo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Corazon Solar Phase II