Dorado Solar
401.35 MW generation in Callahan, TX · In queue since January 2020 · Proposed COD February 2026
401.35 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
3y 5m
IA → COD
2y 8m
Total Duration
3y 5m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-16
Dorado Solar is a proposed 401.35 MW solar generation project located in Callahan County, Texas. The developer is Enbridge Solar (Sequoia I), LLC. The project is in the ERCOT interconnection queue as entry ERCOT-22INR0261, with a queue entry date of January 9, 2020, and a proposed commercial operation date of February 16, 2026. The project's Interconnection Agreement (IA) was executed on June 19, 2023.
The Dorado Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Callahan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Enbridge Solar (Sequoia I), LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68051 Reata 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.