Deville Solar (ERCOT-22INR0262) — Project Summary

Queue ID
ERCOT-22INR0262
Capacity
425.02 MW
Technology
Solar
Status
active
Location
Callahan, TX
Region
ERCOT
Developer
Deville Solar LLC
IA Status
IA Executed

Deville Solar

ERCOT-22INR0262BetaActiveSolarERCOTLBNL + Live

425.02 MW generation in Callahan, TX · In queue since January 2020 · Proposed COD November 2026

425.02 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Status

Signed Aug 2023

Interconnection

Queue → IA

3y 7m

IA → COD

3y 3m

Total Duration

3y 7m

Construction75%
Queue EntryJan 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 29, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-11-21

About

Deville Solar is a proposed solar generation project with a total capacity of 425.02 MW. The project, located in Callahan County, Texas, is being developed by Deville Solar LLC. It consists of 425.02 MW of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-22INR0262, with a queue entry date of January 22, 2020. Its proposed commercial operation date is November 21, 2026. An Interconnection Agreement (IA) has been executed for the project, with an IA date of August 29, 2023. The Point of Interconnection (POI) is the 68051 Reata 345kV substation.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Callahan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Deville Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

68051 Reata 345kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.