Peregrine Solar
301.3 MW generation in Goliad, TX · In queue since January 2020 · Proposed COD December 2024
301.3 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Jun 2021
Queue → IA
1y 5m
IA → COD
3y 6m
Total Duration
1y 5m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-12-30
Peregrine Solar is a proposed 301.3 MW solar generation project located in Goliad County, Texas. The developer is SP-Peregrine Solar LLC. The project is interconnected within the ERCOT queue as entry ERCOT-22INR0283, with a queue entry date of January 7, 2020, and a proposed commercial operation date of December 30, 2024. The interconnection agreement (IA) has been executed as of June 19, 2021.
The proposed project is linked to the existing operating Peregrine Solar plant (EIA ID 65979). The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SP-Peregrine Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 8624 Grissom _x0013_ 8164 Coleto Creek
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PERE_SLR_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26