Bright Arrow Storage
103.56 MW storage in Hopkins, TX · In queue since March 2020 · Proposed COD March 2025
103.56 MW
Capacity
1
Components
Battery
6y 2m
In Queue
IA Executed
IA Status
Signed Mar 2022
Queue → IA
2 years
IA → COD
3 years
Total Duration
2 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-03-01
Bright Arrow Storage is a proposed 103.56 MW battery storage project located in Hopkins County, Texas. The project, developed by RWE Solar Development, LLC, is interconnected within the ERCOT region under queue ID ERCOT-22INR0302. It entered the interconnection queue on March 6, 2020, and has a proposed commercial operation date of March 1, 2025.
The project's Interconnection Agreement (IA) was executed on March 17, 2022. Recent news coverage indicates development activity related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11689 CYCLONE 345 KV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bright Arrow Storage