Inertia BESS
13 MW storage in Haskell, TX · In queue since June 2020 · Proposed COD April 2025
13 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
Signed May 2021
Queue → IA
11 months
IA → COD
3y 11m
Total Duration
11 months
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-04-01
Inertia BESS is a proposed 13 MW battery storage project located in Haskell County, Texas. The project, developed by Inertia Energy Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-22INR0328. It entered the interconnection queue on June 3, 2020, with a proposed commercial operation date of April 1, 2025. The project's Interconnection Agreement (IA) was executed on May 4, 2021.
The proposed project is linked to the existing Inertia Energy Storage operating plant (EIA ID 68874). The point of interconnection is on the tap 345kV 60515 Clear Crossing - 6104 Smoky Hill line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Inertia Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 60515 Clear Crossing - 6104 Smoky Hill
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- INRT_W_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Inertia BESS