Matagorda Solar
101 MW generation in Matagorda, TX · In queue since May 2020 · Proposed COD August 2027
101 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
Signed Jun 2022
Queue → IA
2y 1m
IA → COD
5y 2m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-25
The Matagorda Solar project is a proposed 101 MW solar generation project located in Matagorda County, Texas. Developed by Leeward Renewable Energy Development, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-22INR0342. The project entered the interconnection queue on May 1, 2020, and has a proposed commercial operation date of August 25, 2027.
The project's Interconnection Agreement (IA) was executed on June 8, 2022. The point of interconnection is the 5555 Shropshire 69kV substation. The Matagorda Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Leeward Renewable Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5555 Shropshire 69kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09