Crater BESS
301.17 MW storage in Howard, TX · In queue since May 2020 · Proposed COD March 2028
301.17 MW
Capacity
1
Components
Battery
6 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
Crater BESS is a proposed 301.17 MW battery storage project located in Howard County, Texas. The project, developed by BRP Crater BESS LLC, is interconnected within the ERCOT region under queue ID ERCOT-22INR0347. It entered the interconnection queue on May 20, 2020, with a proposed commercial operation date of March 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The Crater BESS project has been the subject of recent news coverage, appearing in approximately 50 news articles primarily focused on industry developments and deals.
Generated from interconnection queue and public data sources
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Crater BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1025 Falcon Seaboard - 1021 Midland East
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FLCNS_UNIT1
- POI Substation
- Falcon Seaboard Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26